News
Hexal do Brasil
A new pharmaceutical plant including solida production, logistics, and packaging was planned. The new complex of offices and other (multi-purpose) rooms is built on the open countryside.
Projectdata
Client / Building Owner
Koppenhöfer & Partner GmbH / Hexal do Brasil Ltda.
Architect
Mr. Dresing, Mr. Winkler
Time of performance / construction period
2001, 2002
Asset groups
Sanitary Facilities, Heating, Ventilation, Control Technology, AC, Technical Gases, BMS System, Ultrapure Water, Sprinkler Systems, Vacuum Cleaners
Project Details
A new pharmaceutical plant including solida production, logistics, and packaging was planned. The new complex of offices and other (multi-purpose) rooms is built on the open countryside.
The following buildings were constructed:
- a manufacturing hall with solida (8.800m²) and liquida production (450m²) including packaging
- a building housing logistics (3.700m²) and high-bay racking (2.000m²/7.500 palettes)
- a building housing laboratories (1.000m²), a cafeteria (900m²) and meeting rooms (230m²)
- a building housing offices with a total area of 7.300m²
- a mechanical room housing technical installation split up into 5 areas on 7.700m²